Newy 87.8 FM – The Newcastle Inner City Bypass will open in full on Friday 20 November 2026, with the completion of the missing link between Rankin Park and Jesmond.
The Rankin Park to Jesmond project is the fifth and final section of the bypass, which will run between Bennetts Green and Sandgate.
Once open, motorists will be able to bypass 11 sets of traffic lights, and up to 30,000 vehicles a day will come off local roads.
The project is backed by a $488.2 million investment, with $390.6 million from the Australian Government and $97.6 million from the NSW Government.
The bypass is expected to reduce travel times by more than half during morning and afternoon peaks.
A dedicated interchange will provide direct access into the John Hunter Health and Innovation Precinct from the north and south, with the project expected to ease congestion along Croudace and Lookout roads.
The project also includes more than 3.4 kilometres of new and upgraded walking and cycling connections.
Construction involved laying more than 120,000 tonnes of asphalt and supported around 900 jobs.
"For the first time, locals will be able to drive the full length of the Newcastle Inner City Bypass, from Bennetts Green to Sandgate," NSW Minister for Roads Jenny Aitchison said.
The vision for a north-south corridor through Newcastle was first identified in the 1950s, with the first section, Rankin Park to Kotara, opening in 1983.
Finishing work will continue after the opening, including the oversize overmass island at the northern interchange, works at Jesmond Park and landscaping.