Transgrid awarded contract to deliver 110km Hunter Transmission Project
Energy Corporation of NSW(Energy Corporation of NSW)
Newy 87.8 FM – The NSW Government has awarded Transgrid the contract to deliver the 110km, 500kV Hunter Transmission Project from Bayswater to Olney.
Downer and UGL have been appointed as construction partners, with Downer delivering the transmission line and UGL the switching stations and substation upgrades.
The contract follows a procurement process overseen by the Australian Energy Regulator, with the announcement issued by the Energy Corporation of NSW (EnergyCo) on 23 November 2026.
Downer said its transmission line works are valued at approximately $1.1 billion over a three-year construction period.
Downer said planning, design and procurement are expected to start in December 2026, with on-site mobilisation in 2027, subject to final approvals.
The double-circuit overhead line will run from Bayswater in the Upper Hunter to Olney in the Lower Hunter, connecting to the existing transmission network near Eraring.
Between Bayswater and Broke, the line is predominantly within mining, energy and government land, before continuing through the Pokolbin, Corrabare, Watagan and Olney state forests.
The project received NSW Government planning approval in July 2026, subject to 115 conditions.
Fewer than 20 private properties are impacted by the corridor, down from 70 in the preliminary corridor.
The project is expected to create 900 construction jobs, with construction expected to start in 2027.
Business Hunter CEO Bob Hawes said the selection of Downer and UGL "highlights the depth of expertise that already exists in the Hunter".